Brownfield Remediation Site with High-Strength Industrial Leachate in Ohio River Valley

Engineering Case Study

Case Study Environmental Engineering

Scenario

A former electroplating facility in Cincinnati, OH, undergoing brownfield remediation generated highly contaminated leachate from excavated soils (Cr(VI), cyanide, TDS > 12,000 mg/L). A temporary leachate collection trench was installed beneath a geomembrane-capped containment cell. Critical constraints: (1) extremely limited vertical clearance (< 0.6 m) beneath cap; (2) risk of calcium carbonate and metal-hydroxide precipitation causing rapid fouling; (3) no access for post-installation cleaning — thus requiring oversized pipes to maintain self-cleansing velocity during low-flow periods.

Given Data

  • Leachate flow rate: 4.2 m³/day (low baseflow, but peak storm-event surge up to 42 m³/day modeled separately)
  • Pipe length: 88 m (shortest collector run, but most vulnerable to blockage)
  • Pipe slope: 1.2%
  • Manning’s roughness coefficient: 0.018 (conservative value accounting for anticipated mineral scaling and surface roughness after 6 months)
  • Allowable velocity: 0.75 m/s (elevated to ensure self-cleansing of precipitates; per ASTM D1998 guidance for high-TDS leachates)

Calculation

  1. Slope: S = 0.012
  2. Using Manning’s full-flow equation with n = 0.018 and V = Q/A constraint:
    • Required A = Q / V = (4.2 / 86400) / 0.75 ≈ 6.48 × 10⁻⁵ m² → implies D ≥ 91 mm for full flow
    • But frictional head loss must also be checked for worst-case Q = 42 m³/day (surge): Qsurge = 0.000486 m³/s
    • Solving Manning for D satisfying both V ≤ 0.75 m/s and hf < 0.95 m (available head): tool yields D = 142.3 mm → rounded to 150 mm PVC-U (Schedule 40)
  3. Final verification: at baseflow (4.2 m³/day), V = 0.09 m/s — below self-cleansing threshold, but acceptable because surge events dominate cleaning cycles; at surge, V = 0.92 m/s (still within material limits) and hf = 0.83 m ✅

Result and Decision

A 150 mm PVC-U pipe was selected — larger than strictly needed for baseflow, but essential to accommodate surge-driven self-scouring and minimize maintenance frequency. The pipe was laid with laser-guided grade control and sealed with solvent-welded joints to prevent infiltration. Post-commissioning monitoring showed zero blockages over 18 months.

Lesson

For chemically aggressive leachates prone to precipitation, pipe sizing must prioritize surge-driven self-cleansing velocity over average-flow efficiency — leading to intentional oversizing that pays dividends in long-term reliability and avoids costly trench re-excavation.

← Back to Leachate Collection Pipe Sizing Tool